| 1. | One of the functional managers wants to make a major scope change during the execution of the project. The project manager's action should be to: 
| A. | Refuse the change. | 
| B. | Complain to the sponsor. | 
| C. | Detail the impact of the change for the functional manager. | 
| D. | Make the change and go on. |
|
| 2. | In Scope Change Control, the project manager must make sure that: 
| A. | The team is involved | 
| B. | The changes are beneficial | 
| C. | Schedules do not change | 
| D. | The sponsor takes charge |
|
| 3. | As changes are brought forward, the project manager should always: 
| A. | Refuse to consider the change | 
| B. | Install the change immediately | 
| C. | Consider the impact of the change | 
| D. | Stall until given further instructions |
|
| 4. | The one function that must be on the CCB is the: 
| A. | Sponsor | 
| B. | Executive manager | 
| C. | Team lead | 
| D. | Project manager |
|
| 5. | After a change request has been denied, you should: 
| A. | Record it and save it | 
| B. | Get on with the next request | 
| C. | Forget it | 
| D. | Tell the project team |
|
| 6. | Change requests are made against the: 
| A. | Charter | 
| B. | SOW | 
| C. | Executive summary | 
| D. | Project baseline |
|
| 7. | Change requests should be: 
| A. | Formal | 
| B. | Timely | 
| C. | Interesting | 
| D. | Long |
|
| 8. | If change requests are not done formally, this often leads to: 
| A. | Management excellence | 
| B. | A new scope statement | 
| C. | Scope creep | 
| D. | Information creep |
|
| 9. | The Change Control Board should: 
| A. | Be flexible | 
| B. | Have appropriate authority | 
| C. | Include the project manager | 
| D. | All of the above |
|
| 10. | The CEO comes into your office (cubby). He or she asks for changes to be made in the scope of the project but doesn't have enough time to go through a formal procedure, and because everyone on the project actually reports to him or her, it is expected that you get these things done. You should: 
| A. | Run like hell. | 
| B. | Make sure the project team knows you are important enough to talk to the president. | 
| C. | Determine what will happen if the change is made and then report that to the president. | 
| D. | Run like hell. |
|
| 11. | The tools and techniques used to gather, integrate, and disseminate the outputs of project management processes are called a: 
| A. | SOW | 
| B. | Scope Statement | 
| C. | Management system | 
| D. | PMIS |
|
| 12. | The baseline version number of a document is:
|
| 13. | Version control numbers should change when: 
| A. | Major changes are made | 
| B. | Scope change is involved | 
| C. | Any change occurs | 
| D. | The sponsor says so |
|
| 14. | Version control helps make meetings easier because: 
| A. | People like it | 
| B. | It keeps everyone on the same page | 
| C. | It is easy | 
| D. | It is a predecessor to a SOW |
|
| 15. | A formal procedure for sanctioning project work is a: 
| A. | Charter | 
| B. | Scope Statement | 
| C. | Statement of Work | 
| D. | Work authorization |
|
| 16. | Verbal authorization of project work is often seen in ________ projects. 
| A. | Smaller | 
| B. | Strange | 
| C. | Large | 
| D. | Important |
|
| 17. | Procurement items are detailed in the: 
| A. | WBS | 
| B. | SOW | 
| C. | Charter | 
| D. | Scope Statement |
|
| 18. | The acronym for the value of the work already completed on the project is:
|
| 19. | EV, or Earned Value, is the same as:
|
| 20. | PV is the same as:
|
| 21. | If your AC = $25,000 and your EV = $20,000, how are you doing? 
| A. | Over Budget $5,000 | 
| B. | No variance | 
| C. | Under Budget $5,000 | 
| D. | You are in deep yogurt |
|
| 22. | If your AC = $3,000 and your EV = $3,400, how are you doing? 
| A. | $400 | 
| B. | No variance | 
| C. | +$400 | 
| D. | Here's that yogurt again |
|
| 23. | Your Earned Value is $10,000 and your Actual Cost is $8,000. That means that your CPI is: 
| A. | Incomprehensible | 
| B. | .80 | 
| C. | 1.25 | 
| D. | 80 |
|
| 24. | Your Earned Value is $10,000 and your Actual Cost is $12,000. What is your CPI?
|
| 25. | Your EV = $8,000 and your PV = $6,000. What is your SPI?
|
| 26. | Your EV = $500 and your PV = $600. What is your SPI?
|