| 1. | One of your project deliverables is to perform a post-implementation review of the water treatment plant you just delivered. You have been asked to do what? 
| A. | Present all the lessons learned. | 
| B. | Meet with the project sponsor to discuss what could have been improved in your project. | 
| C. | Investigate and report on the plan performance and maintenance requirements. | 
| D. | Meet with your project team and discuss plant support options. | 
| E. | None of the above. |
|
| 2. | Part of the project closure process is to gain formal acceptance. From whom do you need to gain this formal acceptance? 
| A. | The qualify director | 
| B. | The head of the project management office | 
| C. | The project sponsor | 
| D. | The customer | 
| E. | C and D |
|
| 3. | You are the project manager of a project that just went into integration mode. This means that your project 
| A. | Is still running but missing resources | 
| B. | Will be closed due to lack of resources | 
| C. | Resources are being assigned to other areas of the business | 
| D. | Has been accepted by the sponsor and the client | 
| E. | A and C |
|
| 4. | You are the project manager of a project that just went into extinction. This means that your project 
| A. | Is still running but missing resources | 
| B. | Will be closed due to lack of resources | 
| C. | Resources are being assigned to other areas of the business | 
| D. | Has ended before its stated objective | 
| E. | B and D |
|
| 5. | You are the project manager of a project that just went into inclusion mode. This means that your project 
| A. | Is still running but missing resources | 
| B. | Will be closed due to lack of resources | 
| C. | Has become part of the business processes | 
| D. | Has been accepted by the sponsor and the client | 
| E. | A and C |
|
| 6. | Which one of these is not an input to the close project process? 
| A. | Project management plan | 
| B. | Project management information system | 
| C. | Contract documentation | 
| D. | Work performance information | 
| E. | Deliverables |
|
| 7. | Administrative closure is the process that 
| A. | Includes all the activities needed to validate the project products and services | 
| B. | Collects user acceptance of the project product or service | 
| C. | Closes all activities pertaining to a specific project | 
| D. | None of the above |
|
| 8. | The primary output of the project closing process is 
| A. | To formalize and distribute all information pertaining to the project closing | 
| B. | Lessons learned | 
| C. | To release all personnel assigned to the project | 
| D. | To get customer and sponsor approval | 
| E. | B and D |
|
| 9. | Which one of these is not an output of contract closure? 
| A. | Close contracts | 
| B. | Contract file | 
| C. | Lessons learned documentation | 
| D. | Deliverable acceptance | 
| E. | Procurement audits |
|
| 10. | Lessons learned are 
| A. | Best collected at the end of the project | 
| B. | Collected for the historical knowledge base | 
| C. | Only necessary at the end of the project | 
| D. | A store of historical information | 
| E. | Used to collect information about good and bad outcomes throughout the project |
|
| 11. | Product verification pertains to 
| A. | All the activities that verify that the products and services delivered are in line with quality requirements | 
| B. | All the activities that verify that the products and services delivered are in line with project deliverables and sponsor and client satisfaction | 
| C. | All activities that verify tangible assets | 
| D. | A and C | 
| E. | None of the above |
|
| 12. | The main goal of having lessons learned is to 
| A. | Keep the names of the team for prosperity | 
| B. | Close all open contracts | 
| C. | Record variances and the mental state behind corrective and preventive actions taken | 
| D. | Record all the qualitative reasoning behind corrective and preventive actions taken in the project |
|
| 13. | What is the main reason to make sure all contracts are closed at the end of the project? 
| A. | Contracted materials must be returned. | 
| B. | Contractors need to return all excess materials. | 
| C. | Contracts are legally binding. | 
| D. | You would like to avoid any penalties. | 
| E. | None of the above. |
|
| 14. | Work performance information is considered as 
| A. | A necessary process to enter a contract | 
| B. | Required as part of the vendor performance evaluation | 
| C. | Only needed for contracts in distress | 
| D. | A tool and technique for the contract administration process | 
| E. | None of the above |
|