| 1. | The ________ is the document that starts the entire Project Time Management process. 
| A. | Charter | 
| B. | SOW | 
| C. | RFP | 
| D. | Scope Statement |
|
| 2. | Decomposition of the Scope Statement results in the ________. 
| A. | Project plan | 
| B. | WBS | 
| C. | SOW | 
| D. | Schedule |
|
| 3. | You break down the WBS into smaller ________ to get detail so that you can construct a schedule. 
| A. | Work packages | 
| B. | Time components | 
| C. | Sections | 
| D. | Issues |
|
| 4. | When using decomposition in activity definition, the final output is: 
| A. | Deliverables | 
| B. | Work packages | 
| C. | Activities or action steps | 
| D. | Schedule |
|
| 5. | Updates to the WBS during activity definition are often called: 
| A. | Supporting detail | 
| B. | Refinements | 
| C. | Updates | 
| D. | Activities |
|
| 6. | A form of progressive planning is called: 
| A. | Scheduling | 
| B. | Charting | 
| C. | Expanded trial | 
| D. | Rolling wave |
|
| 7. | The major output from activity definition is: 
| A. | The schedule | 
| B. | The activity list | 
| C. | WBS | 
| D. | SOW |
|
| 8. | Other outputs from activity definition are: 
| A. | Activity attributes, Milestone lists | 
| B. | WBS, SOW | 
| C. | Technical requirements, and the WBS | 
| D. | Activity costs, schedule costs |
|
| 9. | Milestones are: 
| A. | Activities with durations | 
| B. | Significant events in the project life cycle | 
| C. | Cost measurements | 
| D. | Denote start and finish of all activities |
|
| 10. | Three types of dependencies are mandatory, discretionary, and ________. 
| A. | Easy | 
| B. | Planned | 
| C. | Internal | 
| D. | External |
|
| 11. | How long is the duration for a milestone? 
| A. | 0 days | 
| B. | 3 days | 
| C. | It depends | 
| D. | 5 days |
|
| 12. | The type of dependency that is used by Microsoft Project is a ________ dependency. 
| A. | Start-to-finish | 
| B. | End-to-end | 
| C. | Finish-to-start | 
| D. | Start-to-end |
|
| 13. | Starting a new computer system before turning the old one off is an example of a(n) ________ dependency. 
| A. | Start-to-finish | 
| B. | End-to-end | 
| C. | Finish-to-start | 
| D. | Natural |
|
| 14. | Which Network Diagramming Method uses dummy activities?
|
| 15. | PDM is also known as what? 
| A. | Activities on nodes | 
| B. | Activities dependencies | 
| C. | Activities on arrows | 
| D. | Activities sequencing |
|
| 16. | PDM stands for: 
| A. | Positive Daily Mechanisms | 
| B. | Process Diagramming Method | 
| C. | Precedence Daily Management | 
| D. | Precedence Diagramming Method |
|
| 17. | Conditional branches can be found in:
|
| 18. | A schematic display of the project's activities and the logical relationships among them is a(n) ________. 
| A. | Technically difficult process | 
| B. | Working Schedule | 
| C. | Project network diagram | 
| D. | Schedule diagram |
|
| 19. | ________ are a high-level compilation of the tasks below them. 
| A. | WBS | 
| B. | Summary tasks | 
| C. | Schedules | 
| D. | PDM |
|
| 20. | The project plan is developed by: 
| A. | The manager of project managers | 
| B. | Executive management | 
| C. | The project team and manager | 
| D. | Sponsors |
|
| 21. | The project schedule is developed in the ________ phase. 
| A. | Execution | 
| B. | Initiation | 
| C. | Planning | 
| D. | Conceptual |
|
| 22. | Estimating databases and other historical data are examples of ________ that might be helpful in estimating durations. 
| A. | Records | 
| B. | Organizational assets | 
| C. | Written data | 
| D. | Electronic information |
|
| 23. | Top-down estimating is also known as ________ estimating. 
| A. | Organizational | 
| B. | Simple | 
| C. | Analogous | 
| D. | Primary |
|
| 24. | Which technique below is the most common simulation technique? 
| A. | GERT | 
| B. | Monte Carlo | 
| C. | Linear Analysis | 
| D. | Decompression |
|
| 25. | Rules of thumb are known as ________. 
| A. | Leveling Heuristics | 
| B. | Common sense | 
| C. | Problem solvers | 
| D. | Monte Carlo analysis |
|
| 26. | Monte Carlo simulation is done using ________ scenarios. 
| A. | Simple | 
| B. | Technical | 
| C. | Common | 
| D. | Multiple |
|
| 27. | What tasks would you Fast Track to shorten the project duration in the Critical Path in Figure 10-9? 
| A. | E & G | 
| B. | B, D, & E | 
| C. | C & F | 
| D. | C & G |
|
| 28. | Doing more activities in parallel is called ________. 
| A. | Fast Tracking | 
| B. | Schedule clearing | 
| C. | Compressed work | 
| D. | Planning compression |
|
| 29. | Bar charts do not show ________. 
| A. | Time constraints | 
| B. | Dependencies | 
| C. | Partial tasks | 
| D. | All of the above |
|
| 30. | The approved project schedule is called the: 
| A. | Sponsored schedule | 
| B. | Performance schedule | 
| C. | Baseline schedule | 
| D. | Approved schedule |
|
| 31. | Anything done to bring expected future schedule performance in line with the project plan is known as ________. 
| A. | Replanning | 
| B. | Schedule arrangement | 
| C. | Corrective actions | 
| D. | Rebaselining |
|
| 32. | If you update the schedule, the updates must be approved by the ________. 
| A. | Project manager | 
| B. | Project Team | 
| C. | Line management | 
| D. | Sponsor |
|
| 33. | Revisions are a special type of schedule updates that make changes to: 
| A. | Costs | 
| B. | Resources | 
| C. | Same as Fast Tracking | 
| D. | Start/Finish Dates |
|
| 34. | Rebaselining should occur only if the current baselines ________. 
| A. | Are off by 10% | 
| B. | Are off by 20% | 
| C. | Make no sense | 
| D. | Are bad |
|