| 1. | The person in the organization that authorizes the commencement of a project is the: 
| A. | Senior Manager | 
| B. | Project Administrator | 
| C. | Sponsor | 
| D. | Project Specialist |
|
| 2. | The document that authorizes the release of organizational resources to the project is the: 
| A. | Statement of Work | 
| B. | Project Design Plan | 
| C. | WBS | 
| D. | Charter |
|
| 3. | The project manager is assigned in the: 
| A. | Charter | 
| B. | Project Plan | 
| C. | SOW | 
| D. | Management Plan |
|
| 4. | Without a ________ the project cannot go forward. 
| A. | Leader | 
| B. | Charter | 
| C. | Project Administrator | 
| D. | WBS |
|
| 5. | A project manager is assigned to a project in the ________ phase of the project. 
| A. | Management | 
| B. | Initiation | 
| C. | Closing | 
| D. | Controlling |
|
| 6. | _________ scope determines the features and functions of the output of the project. 
| A. | Management | 
| B. | Control | 
| C. | Project | 
| D. | Product |
|
| 7. | The work that needs to be done to produce a product/service is included in the: 
| A. | Execution Plan | 
| B. | Product Scope | 
| C. | Project Scope | 
| D. | SOW |
|
| 8. | The tangible measurement or outcome that must be produced to complete a part of a project or the project itself is called a: 
| A. | Work Statement | 
| B. | RFP | 
| C. | Deliverable | 
| D. | Project Plan |
|
| 9. | A description of the final deliverable is one of the best ways to make sure that you are in control of the project in the ______________ phase. 
| A. | Initiation | 
| B. | Closing | 
| C. | Execution | 
| D. | Planning |
|
| 10. | The Work Breakdown Structure is done by: 
| A. | The Sponsor | 
| B. | Senior Management | 
| C. | The Project Manager | 
| D. | The Project team |
|
| 11. | The WBS is done during Scope Definition; Scope Definition comes between: 
| A. | Scope Planning and Scope Change Control | 
| B. | Scope Verification and Scope Change Control | 
| C. | Scope Planning and Scope Verification | 
| D. | Scope Management and Scope Planning |
|
| 12. | Most projects need ________ meeting(s) to do a good WBS. 
| A. | One | 
| B. | Multiple | 
| C. | Long | 
| D. | Interactive |
|
| 13. | A good WBS: 
| A. | Helps pull the team together | 
| B. | Is a roadmap for the project | 
| C. | Defines the scope | 
| D. | All of the above |
|
| 14. | Getting the WBS done is the responsibility of: 
| A. | Senior Management | 
| B. | The Project Team | 
| C. | The Project Manager | 
| D. | The Sponsor |
|
| 15. | The project team is created in the ________ phase. 
| A. | Initiation | 
| B. | Control | 
| C. | Execution | 
| D. | Planning |
|
| 16. | The document that shows the tasks needed to complete the project in detail is the: 
| A. | Statement of Work | 
| B. | Schedule | 
| C. | WBS | 
| D. | Network diagram |
|
| 17. | The single most important position for completing a project successfully is the: 
| A. | President of the company | 
| B. | Sponsor | 
| C. | Project Manager | 
| D. | Scribe |
|